Question
(x + 6) workers complete 40% of a job in 8 days by
working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Find x.Solution
According to the question,
{(x + 6) × 8 × 5}/0.40 = {(x + 2) × 16 × 5}/0.60
Or, 3x + 18 = 4x + 8
Or, x = 10
Hence, value of x is 10.
What does the Capital Adequacy Ratio (CAR), also known as the Capital-to-Risk Weighted Assets Ratio (CRAR), indicate about a bank?
What is the Maximum Age limit to avail MUDRA Loan?
Demand for a commodity refers to?
The EPCG scheme is governed by the Foreign Trade Policy of India and administered by which of the following government body?
RBI recently came up with the latest iteration of its annual report on the financial performance- ‘Report on Trend and Progress of Banking in Indi...
Who is the MD & CEO of Central Depository Services ?
Recently RBI proposed a ___ tier regulatory and supervisory framework for NBFCs.
Which of the following are correct in regard to the austerity measures taken by a country going through adverse economy conditions:
(1) These mea...
The scheme "Pradhan Mantri Matsya Sampada Yojana (PMMSY)" was launched by the Department of Fisheries; Ministry of Fisheries, Animal Husbandry, and Dair...
Consider the following statements regarding social security system in India:
1. National social assistance programme comes under the ministry of ...