(x + 6) workers complete 40% of a job in 8 days by
working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Find x.Solution
According to the question,
{(x + 6) Ă— 8 Ă— 5}/0.40 = {(x + 2) Ă— 16 Ă— 5}/0.60
Or, 3x + 18 = 4x + 8
Or, x = 10
Hence, value of x is 10.
Silicon Carbide is also known by which of the following names?
What is the overall index value of India in the Global Pension Index 2023?Â
Which Indian bank became the first trading cum clearing member at IIBX?
The two famous assemblies in the reign of Harshavardhana were held at?
In New Delhi, India, from February 21 to 23, 2024, which edition of the Raisina Dialogue was held?
On what is the principle of Brahmo Samaj based?
How many trades are covered under the PM Vishwakarma Scheme launched on 17th September 2023?
Which current is a cold ocean current?
Which of the following research organizations will be launching “One Week One Lab” campaign in the month of January 2023 ?
The 'Father of Indian Internet' and former chairman of VSNL passed away, name him?