      Question

      50 men can complete a piece of work in 15 days. 10 men

      started the same work and worked for 10 days, and then joined by β€˜x’ more men such that the remaining work is completed in 10 days. Find the value of β€˜x’.
      A 50 Correct Answer Incorrect Answer
      B 52 Correct Answer Incorrect Answer
      C 53 Correct Answer Incorrect Answer
      D 55 Correct Answer Incorrect Answer

      Solution

      According to the question, 50 Γ— 15 = 10 Γ— 10 + (10 + x) Γ— 10 Or, 10 + x = (750 – 100) Γ· 10 Or, 10 + x = 65 Or, x = 55