Question
50 men can complete a piece of work in 15 days. 10 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remaining work is completed in 10 days. Find the value of ‘x’.
More Time and work Questions
- ‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to finish the task.
- A and B together do a job in 12 days. A alone does it in 20 days. How many days for B alone?
- David can complete a work alone in 30 days, while Ethan can complete the same work in 50 days. Both of them started the work together and worked till 96% o...
- A can complete a piece of work in 80 days, B takes 20% more time than A to complete the same work while C takes 25% more time than B to complete the whole ...
- An inlet pipe can fill a tank in 15 minutes when there’s no leakage. However, due to a leak in the tank, it takes 21 minutes to fill it completely. How lon...
- 45 people can repair a road in 10 days working 6 hours a day. In how many days can 30 people working 6 hours a day complete the same work?
- P and Q individually can complete the work in 26 days and 39 days respectively. If the time taken by R alone to complete the work is 1.25 times the time ta...
- 24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which...
- A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and C i...
- ‘A’ is 100% more efficient than ‘C’, while ‘B’ is 200% more efficient than ‘A’. Together, they complete a task in 15 days. After ‘A’ and ‘C’ work for 9 day...