Question
60 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remaining work is completed in 12 days. Find the value of ‘x’.
More Time and work Questions
- Bhuvan can finish a task by himself in 15 days, while when working together, Anoop and Bhuvan can complete the same task in 8 days. Anoop starts the work a...
- Sushil can type 40 lines in 20 minutes but he leaves 8% margin on each line. In how much time he will type 46 pages with 80 lines on each page in which he ...
- P and Q together finish a piece of work in 12 days. R works at half the efficiency of P. Q alone can finish the work in 30 days. Now if Q and R work togeth...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 60% of the same work in 20 days. If they work together for the entire time and get paid Rs.1450, then fin...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
- Anu can finish 25% of an assignment in 10 days, whereas Tanya can do 30% in 12 days. Anu works on it for 16 days and leaves. How long will Tanya take to wr...
- A task can be done by ‘p’ men in 32 days. If the team had 8 more men, the work would finish in 24 days. Find the value of ‘p’.
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.
- 40 women working 10 hours a day take 12 days to complete a project. How many women working for 7 hours a day are needed to complete twice the given project...