Question
Aisha and Neel can complete a job alone in 66 days and 99 days respectively. Working together, they earn a total wage of Rs. 11,550. How much does Aisha receive?
More Time and work Questions
- 5 girls can do a piece of work in 9 days, 4 boys can do the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can d...
- P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P...
- 'Akshay' alone takes 18 days to finish a work while 'Bhim' alone takes 24 days to finish the same work. If 'Akshay' and 'Bhim' work on alternate days start...
- 'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' and '...
- Sneha and Meena can complete a project in 24 days and 60 days respectively. Sneha began working first. After how many days should Meena step in so that the...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
- A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x − 2) units per day. They work together for 9 days and the r...
- Bharti, Chiku, and Diksha complete 30%, 40%, and 20% of a task in 6 days, 12 days, and 8 days, respectively. How many days will it take for them to collect...
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘8a’ hours respectively. If they together can complete half of the work in 8 hours, then...
- There are three taps of diameter 2 cm, 3 cm, and 4 cm, respectively. The ratio of the water flowing through them is equal to the ratio of the square of the...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt