Question
A and B together can complete a work in 12 days, and B
alone can complete it in 20 days. How many days will A take to complete the work alone?Solution
Work done by A and B in one day = 1/12. Work done by B alone in one day = 1/20. Work done by A alone in one day = 1/12 - 1/20 = (5 - 3) / 60 = 2/60 = 1/30. A will take 30 days to complete the work alone. Correct Option: c
What kind of accolades did Tank Cascades garner in 2017, as sanctioned by UNESCO and FAO?
What is/are the reasons for low profitability and substantial value erosion to the principal shareholder-the government?
(A) The continuous deter...
Why was an expansion in plant life observed under warm temperature?
Which of the following is most similar in meaning to the word 'chronic' as used in the passage?Â
Choose the word which is most nearly the same in meaning to the word âprognosisâ as used in the passage.
What does the warmth in the oceans limit?
What led to the author warning the readers that they had to be careful while using the railways, or they might waste their time unnecessarily?
What caused the damage in the author’s house?
He also stressed that the ongoing visit (A)/by the Pakistan Prime Minister to Moscow (B)/will in no way affect ties between India and Russia (C).
Which of the following words is the most opposite in meaning to the word â depletingâ as used in the passage ?