Question
A and B together can complete a work in 12 days, and B alone can complete it in 20 days. How many days will A take to complete the work alone?
More Time and work Questions
- 'A', 'B' and 'C', alone can do some work in 28 days, 35 days and 70 days, respectively. If they work together for wages of Rs. 6,600, then find the differe...
- A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by C i...
- A task can be completed in 15 days when Akash and Bittu work together. Akash is 30% more efficient than Bittu. If both started the task separately and Akas...
- If 14 men working 14 hours a day can make 14 quilts in 14 days, then in how many days 28 men working 28 hours per day will make 28 quilts?
- A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 4 days, after which B leaves. In how many more days will A c...
- Chacha and Bhatija can complete a work in 48 days. In how many days Chacha alone does the 2/3rd of the total work if they start working together after 40 d...
- A can complete a work in 12 days and B can complete the same work in 18 days. A works alone for 4 days and then B alone finishes the remaining work. In how...
- If Pawan takes twice the time that Qureshi takes or three times the time that Raju takes to finish a task, and all three working together can complete it i...
- 2 assistants are as efficient as one senior officer. If 40 assistants prepare 100 reports in 5 days, how many senior officers are needed to prepare 100 rep...
- ‘A’ and ‘B’ can do a piece of work in 10 days and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt