Question

'I' can finish a piece of work in 14 days and 'J' in 21 days. 'I' works for the first day, then 'J' works for the next two days. How many days will it take to complete the work following this pattern?

A 18 days
B 6 days
C 14 days
D 20 days
Practice Next