Question
Arun and Bala, alone can complete a work in 20 days and 30 days, respectively. They started the work together and left after 8 days such that the remaining work is completed by Charan alone in 8 days. If the total wage fixed for completing the work is Rs. 480, then find the share received by Charan.
Solution
Let total work = 60 units {LCM of 20 and 30} So, efficiency of βArunβ = (60/20) = 3 units/day Efficiency of βBalaβ = (60/30) = 2 units/day Amount of work done by Arun in 8 days = 3 Γ 8 = 24 units Amount of work done by Bala in 8 days = 2 Γ 8 = 16 units Amount of work done by Charan = 60 β (24 + 16) = 20 units Ratio of amount of work done by Arun, Bala and Charan = (24 : 16 : 20) = (6 : 4 : 5) Required wages of Charan = {5/(6 + 4 + 5)} Γ 480 = Rs. 160
- A alone can complete 50% of a work in 10 days while B takes 8 days more than A to complete it. If B and C together can complete the work in 12 days, then f...
- βAβ can do a piece of work in 12 days. βBβ can do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then fin...
- B is 20% more efficient than A. If B was 60% more efficient than A, then, B could complete the work in 18 days lesser than days taken by A. What fraction o...
- An elephant can do a work as fast as two horses βAβ and βBβ can do it by working together. If horse βAβ alone can complete the work in 38 hours and horse β...
- A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450...
- Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how many d...
- A alone can complete a piece of work in 18 days and B alone can do it in 24 days. They work together for 6 days, after which A leaves. In how many more day...
- There is enough food in a camp to last for 50 days if each of the 40 soldiers present at the camp eat 2 times a day. After 20 days, 40 more soldiers joined...
- Mohan, Sohan, and Rohan alone can finish a piece of work in 50, 100, and 150 days respectively. They start the work together, but Mohan leaves after 8 days...
- 25 laborers working 7 hours daily can finish a road in 16 days. If 35 laborers work 8 hours each day, how many days are needed?