    Question

    A and B individually can complete the work in 32 days

    and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time taken by A and B together to complete the work, find the time taken by C to complete the work while working alone.
    A 21 days Correct Answer Incorrect Answer
    B 27 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 24 days Correct Answer Incorrect Answer
    E 12 days Correct Answer Incorrect Answer

    Solution

    Time taken by A and B together to complete the work = (32 × 48)/ (32 + 48) = 19.2 days Time taken by C alone to complete the work = 1.25 × 19.2 = 24 days