Question
‘n’ men working 12 hours a day can complete a work
in 15 days while (3n – 8) men working 12 hours a day can complete the same work in 9 days. In how many days can (n + 2) men working 5 hours a day complete the same work?Solution
According to the question, (n × 12 × 15) = {(3n – 8) × 12 × 9} => 5n = 9n – 24 => n = 6 Let the number of days taken by (n + 2) = 8 men be ‘x’ days Therefore, (6 × 12 × 15) = (8 × 5 × x) Therefore, x = 27 days
The term ‘Fair Use’ is associated with which type of IPR?
The Constitution provides for the establishment of Public Service Commission
I. For the ...
Principle of Res Judicate is contained in which section of Indian Evidence Act 1872
Where any electronic record, purporting or proved to be ___________ years old, is produced from any custody which the Court in the particular case consi...
What are Eligible Companies under section 76 of the Companies Act, 2013?
The total amount of deductions from wages of employees should not exceed _______________.
Ensuring the safety, health and welfare of the employees is the primary purpose of the _________________
Article 21A of the Constitution was added to
A civil court cannot issue commission in the following case
When is criminal conspiracy said to be done by a person?