Question
P, Q & R can finish a work in 10 days, 15 days, and 20 days, respectively, working alone. P and Q work on the first day, P and R work on the second day, P and Q work on the third day, and so on till the work is completed. In how many days the work will be completed?
More Time and work Questions
- Ram can do a work in 60 days while Mohan can do the same in 84 days. If Ram work for 'x' days while Mohan work for ' x + 2' days then one-third of the work...
- Two efficient workers or three non-efficient workers can complete a certain task in 20 days. If each efficient worker improves their efficiency by 33(1/3)%...
- 25 laborers working 7 hours daily can finish a road in 16 days. If 35 laborers work 8 hours each day, how many days are needed?
- A and B alone can complete a work in 20 and 30 days, respectively. 50% of the work is completed by C in 5x days, and the remaining work is completed by A a...
- If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
- Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can Deepak...
- 20 men or 40 women can complete a piece of work in 24 days. A man and a woman together complete the work and receive a total wage of Rs. 12,000. Find the d...
- A can do a piece of work in 12 days and B can do it in 18 days. In how many days will they complete the work together?
- M and N together complete a work in 10 days, while N alone does it in 16 days. If the efficiency of M to O is in the ratio 5:6, what is the ratio of effici...
- ‘A’ and ‘B’ can complete a certain work in 15 days and 10 days, respectively. They started working together and worked till completion of the work for whic...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Then ATQ- First day - P + Q =6+4 =10unit second day-P + R=6+3 =9unit third day P+Q=6+4=10unit total work of three days =10+9+10 =29unit so 58units completed of total work = 3×2 =6days remaining work =60-58 =2 unit so, the remaining work will be completed by P+R = 2/9days Total days = 6+2/9 =56/9days