Question
P, Q & R can finish a work in 10 days, 15 days, and 20
days, respectively, working alone. P and Q work on the first day, P and R work on the second day, P and Q work on the third day, and so on till the work is completed. In how many days the work will be completed?Solution
Then ATQ- First day - P + Q =6+4 =10unit second day-P + R=6+3 =9unit third day P+Q=6+4=10unit total work of three days =10+9+10 =29unit so 58units completed of total work = 3×2 =6days remaining work =60-58 =2 unit so, the remaining work will be completed by P+R = 2/9days Total days = 6+2/9 =56/9days
Todarmal, one of the Navaratnas of Akbar, belonged to which of the following districts of Uttar Pradesh?
India's insurance penetration is approximately:
The FAST Trade Connect e-Platform aims to achieve which of the following goals?
Which of the following international airports has got the title of World’s Best Airport 2022?
The concept of the Eightfold Path is a part of which subject matter?
Which is not a factor responsible for soil formation in given options?
Who won the Indira Gandhi Peace Prize for 2024?
____ state has won the UN-Habitat’s World Habitat Awards 2023 for Jaga Mission?
When is “World Biofuel Day” observed worldwide?
Microsoft has collaborated with _________ to accelerate the rapid democratization of data and intelligence that will help businesses increase productivi...