Question
P, Q & R can finish a work in 10 days, 15 days, and 20
days, respectively, working alone. P and Q work on the first day, P and R work on the second day, P and Q work on the third day, and so on till the work is completed. In how many days the work will be completed?Solution
Then ATQ- First day - P + Q =6+4 =10unit second day-P + R=6+3 =9unit third day P+Q=6+4=10unit total work of three days =10+9+10 =29unit so 58units completed of total work = 3×2 =6days remaining work =60-58 =2 unit so, the remaining work will be completed by P+R = 2/9days Total days = 6+2/9 =56/9days
In terms of analytical scope, farm management is primarily concerned with decision-making at the:
As a general rule, symptoms of nitrogen deficiency is first noticeable in:
The measurement of drought is expressed inÂ
The first Indian Cooperative Societies Act was passed in the year:
Autocidal pest management refers to
Average share of agricultural credit to total priority sector lending decreased from 63.73 per cent in 2009-10 to ……………% 2019-20.
...Which is the precursor of ethylene?
Match List-I with List-II and select the correct answer using the codes given below the lists.
Match List I with List II
Choose the correct answ...
Tomato originated in: