Question
'Arun' alone can complete 60% of the work in 15 days,
while 'Arun' and 'Bhaskar' together can complete 80% of the work in 7.5 days. Find the time taken by 'Bhaskar' alone to finish the work.Solution
Time taken by 'Arun' alone to complete the work = (15/0.6) = 25 days Time taken by 'Arun' and 'Bhaskar' together to finish the work = (7.5/0.80) = (75/8) days Let, the total work be LCM of [25 and 75] = 75 units So, the efficiency of 'Arun' = (75/25) = 3 units/day Sum of efficiencies of 'Arun' and 'Bhaskar' together = [75/(75/8) ] = 8 units/day So, the efficiency 'Bhaskar' = 8 - 3 = 5 units/day Time taken by 'Bhaskar' alone to finish the work = (75/5) = 15 days
Which one of the following combinations is incorrect?
If "DOG" is coded as "EPI", how will "CAT" be coded?
What was India’s rank in the global startup ecosystem index 2021 ?
Who has been recently appointed as the new chairman of ISRO ?
How many women are expected to benefit from Odisha’s Subhadra Yojana by 2028-29?
Nagaland became the first Indian state to implement which type of insurance scheme?
Bengal Sati Regulation, 1829 was brought out by which Governor General?
Where was the All-India Muslim League established in 1906?
Which national park is located on an island in Lake Superior?
What was the GST evasion amount found in the online gaming sector during FY24?