      Question

      Efficiency of a man is 20% more than that of a woman.

      (n - 10) men working 6 hours a day can complete a task in 15 days, whereas (n - 9) women working 8 hours a day can complete the same task in 12 days. Find the time taken by (n - 3) men and (n - 4) women working 9 hours a day to complete the task.
      A 2 days Correct Answer Incorrect Answer
      B 3 days Correct Answer Incorrect Answer
      C 4 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer
      E 6 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of a woman be '5e' units/day. Then, efficiency of a man = (6/5) Γ— 5e = '6e' units/day. ATQ; (n - 10) Γ— 6 Γ— 15 Γ— 6e = (n - 9) Γ— 8 Γ— 12 Γ— 5e Or, 540n - 5400 = 480n - 4320 Or, 60n = 1080 Or, 'n' = 18 Total work = (n - 10) Γ— 6 Γ— 15 Γ— 6e = 8 Γ— 6 Γ— 15 Γ— 6e = '4320e' units So, required number of days to complete the work = 4320e Γ· [(15 Γ— 6e + 14 Γ— 5e) Γ— 9] = 4320e Γ· (160e Γ— 9) = 4320e Γ· 1440e = 3 days