Question
P does one fourth as much work as Q in two third of the
time. If together they take 24 days to complete the work, how much time shall Q take to do it?Solution
Let the whole work be done by Q in x days In 2/3 rd of time work by P = 1/4 1/4 of work is done by P in 2/3x days Whole work is done by P in (4 × 2)/(3× x) days = 8/3x days => 1/x + 3/8x = 1/24 => (8+3)/(8x) = 1/24 => x = 33 days
An object is placed 10 cm from a convex mirror of focal length 15 cm. Find the position of the image.
Which among the following is not a characteristic of transition metals?
What is the phenomenon of light splitting into colors when passing through a prism? Â
An image formed by a plane mirror is ______.
What is the value of acceleration due to gravity at the center of the earth?
Which of the following is not a natural polymer?
If resistances R,2R,4R,8R… are connected in parallel, the equivalent resistance is:
What is the minimum escape velocity of rocket to be launched into space?
What is the unit of power in an electrical circuit? Â
An electron in a hydrogen atom de-excites from the 4th to the 2nd level. The wavelength of emitted photon falls in which series?