Question
βXβ and βYβ together can complete a work in 16
days, while βYβ and βZβ together can complete the work in 10 days. If βYβ takes 20 days to complete the work alone then find the time taken by all three together to complete 45% of work.Solution
Let the total work = 80 units Efficiency of (X + Y) = 80/16 = 5 units/day Efficiency of (Y + Z) = 80/10 = 8 units/day Efficiency of βYβ = 80/20 = 4 units/day Efficiency of (X + Y + Z) = (1 + 4 + 4) = 9 units/day Required time taken = (0.45 Γ 80)/9 = 4 days
Australia recently implemented a social media ban for which specific demographic group?
What is the significance of the "e-Filing" system introduced under the e-Courts project?Β
In which of the following years was the Child Marriage Restraint Act passed?
Mouma Das, who received Padma Shri Award in 2021, is a player of which of the following sports?
Who among the following were awarded the Nobel Peace Prize for 2018?
In the RT-PCR examination, the term CT stands for:
Who among the following Delhi Sultanate rulers took the policy of βblood and ironβ to deal with the Mewati community?
Till which year did the High Court of Delhi continue to exercise jurisdiction over Himachal Pradesh?
In which year was the Jammu and Kashmir Reorganization Act passed?
Which of the following is considered as a good indicator of economic growth?