Question
Virat can do a piece of work in 26 days and Sachin can
do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work will completed by Sachin, then how much rupee Sachin earned?Solution
Assume total work = LCM (26, 39) = 78 If the entire work is 78 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 5 days, Virat completes 15 units and got Rs.3000 i.e. Rs.200 per unit. Remaining work = (78 – 15)unit = 63 unit ∴ Sachin earning = Rs.63 × 200 = Rs. 12600
Statement: The Ministry of Civil Aviation has proposed amendments to the Civil Aviation Requirements to establish a National No-Fly List and quantify p...
Statement: The alumni of the institute returned to rescue crumbling building of 112-year-old alma mater.
I. The Building of the institute was b...
Statement: Automobile majors began the new fiscal on a strong note, posting high double-digit growth in their domestic passenger vehicle sales.
...
Statement : The mutual fund market is growing at more than 30% in terms of new assets under management.
I . People are slowly moving from inves...
Statement: Farm fires, being touted as the major reason for unbreathable Delhi air, are shown to account for only 40% of the current spell of deadly ha...
Statement: The rail security helpline was flooded with complaints on catering and cleanliness in the trains.
I. Railways has initiated a new he...
Statement : There are no river sand quarries employing machines and sand extraction is done manually and transportation through carts.
I. The r...
Which of the following statements is an example of deductive reasoning?