Question
Virat can do a piece of work in 28 days and Sachin can
do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will completed by Sachin, then how much rupee Sachin earned?Solution
Assume total work = LCM (28, 42) = 84 If the entire work is 84 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 4 days, Virat completes 12 units and got Rs.1800 i.e. Rs.150 per unit. Remaining work = (84 – 12)unit = 72 unit ∴ Sachin earning = Rs.72 × 150 = Rs. 10800
What is the top speed of the Indian Coast Guard’s Next Generation Offshore Patrol Vessel under construction?
The G20 Summit in 2024 was held in which city
Who has been crowned as the ‘Miss World 2022’?
Which organization has signed an MoU with the Indian Air Force for the integration of futuristic Weapons and Sensors for LCA Tejas aircraft?
Which of the following company had partnered with Reliance General Insurance to provide motor insurance in India?
The ICC has partnered with _______ to amplify awareness around mental health and well-being of children and adolescents throughout the men's T20 World Cup.
What temperature range can the DRDO’s HIMKAVACH clothing system withstand?
What is the estimated growth rate of India's real GDP for the fiscal year 2023-24, as per the first advance estimates released by the National Statistic...
In 2025, RBI cut the policy rate by 125 basis points to:
Which venue hosted the ICC World Test Championship Final in 2025 where South Africa defeated Australia?