Virat can do a piece of work in 28 days and Sachin can
do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will completed by Sachin, then how much rupee Sachin earned?Solution
Assume total work = LCM (28, 42) = 84 If the entire work is 84 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 4 days, Virat completes 12 units and got Rs.1800 i.e. Rs.150 per unit. Remaining work = (84 – 12)unit = 72 unit ∴ Sachin earning = Rs.72 × 150 = Rs. 10800
In a portfolio investment?
Factor endowment theory is also known as
a. Modern theory of international trade.
 b. Classical theory of...
Refer to the below table and calculate the NNPmp
Which of the following is not an example of market failure?
If r xy = 0, then:
As per the regression data available: Wage = 11 + 0.24age - 0.23Illiterate + 0.14Married - 0.27Married*Illiterate, where the variables are self-e...
For a monopoly firm, which of the following equalities is always true?
With the rise in price from ₹ 8 to ₹ 14. Total expenditure on the commodity rises by 40% and becomes ₹ 1,120. Calculate the price elasticity of de...
The Phillips curve shows the trade-off between ----- and -----?
Which of the following statements is NOT correct in the context of quantity theory of money?