Question
Virat can do a piece of work in 28 days and Sachin can
do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will completed by Sachin, then how much rupee Sachin earned?Solution
Assume total work = LCM (28, 42) = 84 If the entire work is 84 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 4 days, Virat completes 12 units and got Rs.1800 i.e. Rs.150 per unit. Remaining work = (84 – 12)unit = 72 unit ∴ Sachin earning = Rs.72 × 150 = Rs. 10800
NSE was established in the year? Â
National Financial Switch is run by whom ?
What is FCCB?
What is the main objective of KYC guidelines followed by Banks?
I- It helps prevent banks from using criminal networks.
II- KYC helps the ...
If a bond is issued when prevailing interest rates are 8% at Rs.1,000 par value with a 8% annual coupon. Which of the following is NOT correct?
...Which of the following is not one of the pillars of Basel III?Â
Which of the following is NOT currently considered legal tender in India as of late 2025?
TReDS is the acronym for which of the following?
A dollar denominated instrument, tradable on stock exchange in Europe or private placement in USA, representing one or more shares of the issuing compa...
........................................is a contractual agreement made between two parties, in which one party agrees to pay for potential losses or da...