Question
Virat can do a piece of work in 28 days and Sachin can
do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will completed by Sachin, then how much rupee Sachin earned?Solution
Assume total work = LCM (28, 42) = 84 If the entire work is 84 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 4 days, Virat completes 12 units and got Rs.1800 i.e. Rs.150 per unit. Remaining work = (84 – 12)unit = 72 unit ∴ Sachin earning = Rs.72 × 150 = Rs. 10800
Where is the headquarters of IRDAI located?
If 15 March 2022 was a Tuesday, what day of the week was 15 March 2020?
Consider the following statements:
1. Alluvial soil is rich in chemical properties and is capable of yielding Rabi and Kharif crops.
...
Which of the following statements are correct in regards to Gaganyaan Mission?
- India’s 1st human space mission to be l...
Which is illegal as per law?
The product of two positive numbers is 3920. If one number is five times the other, then the sum of the two numbers is:
Light year is a measure of
What is the penalty for non-compliance with the provisions of the Maternity Benefit Act, 1961?
What is the need to balance chemical equations?Â
According to the Social Security Code, 2020, the employer's contribution to the deposit-linked insurance fund set up under the insurance scheme should n...