ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!

  • google app store apple app store
  • тЬЦ

      Question

      A can do a piece of work in 15 days, B is 25% more

      efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:
      A 3 days Correct Answer Incorrect Answer
      B 2(1/2) days Correct Answer Incorrect Answer
      C 4 days Correct Answer Incorrect Answer
      D 3 (1/2)days. Correct Answer Incorrect Answer

      Solution

      Let efficiency of A be 100 ⇒ Efficiency of B = 100 + (100 × 25%) ⇒ Efficiency of B = 100 + 25 = 125 ⇒ Efficiency of C = 125 + (125 × 40%) ⇒ Efficiency of C = 125 + 50 = 175 ⇒ Ratio of efficiency of A тИ╢ B тИ╢ C = 100 тИ╢ 125 тИ╢ 175 ⇒ Ratio of efficiency of A тИ╢ B тИ╢ C = 4 тИ╢ 5 тИ╢ 7 A work for 15 days with efficiency 4 unit ⇒ Total work done by A = 15 × 4 = 60 unit Now, (A + C) together work for 3 days. ⇒ Total efficiency of A and C together = 4 + 7 = 11 unit/day ⇒ Total work done by A and C together = 11 × 3 = 33 unit ⇒ Remaining work = Total work - Work done by A and C together ⇒ Remaining work = 60 - 33 ⇒ Remaining work = 27 unit ⇒ Total efficiency of A and B together = 4 + 5 = 9 unit/day ⇒ Required number of days = (27/9) = 3 days ⇒ Time required to complete remaining work = 3 days. ∴ Time required to complete remaining work is 3 days.

      Practice Next
      More Time and work Questions
      ask-question