Question
A alone can complete a piece of work in 15 days, and B
alone can complete it in 20 days. They work together, but every third day B does not work. In how many days will the whole work be completed?Solution
Aβs rate = 1/15 per day. Bβs rate = 1/20 per day. Together = 1/15 + 1/20 = 7/60 per day. Work pattern over 3 days: Day 1: A + B β 7/60 Day 2: A + B β 7/60 Day 3: A only β 1/15 = 4/60 Total in 3 days = (7 + 7 + 4)/60 = 18/60 = 3/10. Total work = 1. Number of full 3-day cycles needed for most of the work: After 3 cycles (9 days), work done = 3 Γ (3/10) = 9/10. Work remaining = 1 β 9/10 = 1/10. On the 10th day, both A and B work: work done = 7/60 per day. Fraction of the 10th day needed: (1/10) / (7/60) = (1/10) Γ (60/7) = 6/7 day. Total time = 9 + 6/7 days = 9 (6/7) days.
Select the option that arranges sentences B, C, D and E in a logical sequence.
Sentences A and F are static.
A. Douglas had a childhood fe...
The philosophy professor stand (A) / before his class with (B) /some items on the table in front of him. (C)/No error(D).
Given below are four jumbled sentences. Select the option that gives their correct order. Β
A. Far below he saw green meadows and in their midst...
Given below are five jumbled sentences. Select the option that gives their correct logical sequence.
A: While the exact cause is debated, some...
Which of the following is the third sentence after rearrangement?
Given that 1 is the first sentence, which of the following will be the FOURTH sentence after rearrangement?
Which of the following would be the SECOND statement after rearrangement?
Which of the following would be the THIRD statement after rearrangement?
In the questions given below, a sentence has been broken down into four fragments labelled (A), (B), (C), and (D) and arranged, not necessarily in the ...
Which of the following would be the SECOND statement after rearrangement?