Question
A alone can complete a piece of work in 12 days and B alone can complete it in 18 days. If they work together, in how many days will they complete the work?
More Time and work Questions
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- The ratio of the efficiency of A, B and C is 3:4:5, if they can complete a work in 18 days then A can complete 60% of the work in how many days?
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- ‘A’ alone can do some work in 13 days. ‘B’ and ‘C’ together can do the same work in 18 days. If ‘B’ is half as efficient as ‘A’, then find the time taken b...
- If a group of 12 boys and 18 girls together can complete a task in 24 days, and a team of 6 girls alone can finish the same task in 96 days, how long will ...
- 14 chefs can cook 21 meals in 7 hours. How much time will 10 chefs take to cook 30 meals?
- 25 employees working 9 hours a day take 20 days to complete a project. How many employees working for 8 hours a day are needed to complete twice the given ...
- A can finish a job in 15 days and B can finish the same job in 20 days. In how many days can they finish it working together?
- 40 men take 15 days to finish some work. If the work is to be finished in 8 days, then how many additional men should be hired?
- A and B can complete a task together in 8 days, while B alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which B comp...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)