Question
Sohan completes half the work done by Ramesh in 3/4 of
the time. If they together can complete the work in 20 days, how much time will Ramesh take to complete the work?Solution
ATQ,
Let time taken by Ramesh to complete the work = t days
Sohan takes 2 × (3t/4) = 6t/4 = 3t/2 days.
Efficiency of Ramesh = 1/t,
Efficiency of Sohan = 2/3t.
Total efficiency = 1/t + 2/3t = 1/20
Solving for t, we get t = 30 days.
What will be the difference between the marks secured by E and D?
Who among the following manufacture biscuits?
Statement: Â Â Â Â
 Only a few Gold are Silver         Â
Only a few Gold are Diamond     Â
Conclusion:    �...
Four of the following five are alike in certain way based from a group, find the one that does not belong to that group?
Which of the following statements is/are true?
How many persons play between R and U?
Who among the following person was born in the same month along with B?
How many boxes are kept above the one that contains Papaya?
How many floors are there above G’s floor?
Who among the following attends conference in Bhutan and in which day?