Question
Sohan completes half the work done by Ramesh in 3/4 of
the time. If they together can complete the work in 20 days, how much time will Ramesh take to complete the work?Solution
ATQ,
Let time taken by Ramesh to complete the work = t days
Sohan takes 2 × (3t/4) = 6t/4 = 3t/2 days.
Efficiency of Ramesh = 1/t,
Efficiency of Sohan = 2/3t.
Total efficiency = 1/t + 2/3t = 1/20
Solving for t, we get t = 30 days.
A instigates B to murder C. B refuses to do so. In this case which of the following is true statement?
When two or more persons are fighting in a public place they are said to commit?
Article 14 guarantees equality before law and equal protection of law to
Abetting commission of offence by public or more than _____ people is punishable with 3 years of imprisonment.
The first Annual General Meeting of the company shall be held ______________
Who can be appointed as the President of the NCLT?
In case of a document 30 years old, Court_____________.
The Bharatiya Nyaya Sanhita, 2023 lays down that an act endangering sovereignty, unity and integrity of India shall be punished with_______________
When a riot is committed for the benefit of some person he is:
The amount payable on application on every security shall _____________of the security or such other percentage or amount, as may be specified by the Se...