Question
Sohan completes half the work done by Ramesh in 3/4 of
the time. If they together can complete the work in 20 days, how much time will Ramesh take to complete the work?Solution
ATQ,
Let time taken by Ramesh to complete the work = t days
Sohan takes 2 × (3t/4) = 6t/4 = 3t/2 days.
Efficiency of Ramesh = 1/t,
Efficiency of Sohan = 2/3t.
Total efficiency = 1/t + 2/3t = 1/20
Solving for t, we get t = 30 days.
? = (597.98 ÷ (6.97 2.01 – 3.1)) × 12.9
1153, 1206, ?, 1326, 1393, 1464
What is the least number of square tiles required to pave the floor of a room 11 m 47 cm long and 6 m 82 cm broad?
Which of the following statements is true about LPP?      Â
What is the value of 8 √ 4 × 16 √ 4?Â
If logâ‚“(81) = 4/3, find x.
Calculate the percentage contribution of the South branch's total revenue to the company's total revenue over the three years (2021-2023).
115, 138, 163, 190, 219, ?
A man drives at a steady speed of 75 km/h for 4 hours, followed by another stretch of 3 hours at a consistent speed of 40 km/h. What is his average spee...
A company’s quarterly sales (in lakh units) are:
Q1: 18, Q2: 24, Q3: 21, Q4: 27
Find the percentage increase from...