Question
N workers can complete a piece of work in 50 days. When
5 more workers joined, then the work got completed in 40 days, then what is the value of N?Solution
As we know, M1 × D1 = M2 × D2 Where, M = number of Men and D = number of Days ⇒ N × 50 = (N + 5) × 40 ⇒  5N = 4N + 20 ⇒  N = 20 Hence, the value of N = 20
The government securities market in India is regulated by _______
A company invests ₹60,000 in a project that generates ₹15,000 as net annual cash inflow. What is the payback period of the project?
Plant purchased for ₹6,00,000. Depreciation for year = ₹1,00,000. Closing balance of Plant = ₹10,00,000. Opening balance was ₹5,00,000. Calculat...
A company purchased machinery for ₹50,00,000 on 1st April 2020. Installation cost was ₹5,00,000. Residual value ₹3,00,000, useful life 5 years. On...
EOQ (Economic Order Quantity) is a model used in inventory control to determine:
What is the maximum limit for insurance coverage provided by the Deposit Insurance and Credit Guarantee Corporation (DICGC) in India?
The audit that is made compulsory under statute is called _________.
Net Working Capital (NWC) is defined as:
ABC Ltd., a manufacturing company, undertook a series of transactions during the financial year 2024–25. It purchased a new plant worth ₹1,000 lakh ...
A company begins construction of a qualifying asset funded partly from general borrowings. Work was suspended for 5 months due to a strike. Should borro...