Question

Time taken by 24 men working 8 hours a day to complete a work is 30 days whereas time taken by 32 women working 9 hours a day to complete the work is 25 days. Find the time taken by 18 men and 15 women working together 12 hours a day to complete the work.

A 16 days
B 14 days
C 18 days
D 20 days
E 12 days