Question
A and B together can do a work in 12 days. If A can
alone do the same work in 18 days, then in how many days B alone will do the same work?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (12, 18) = 36 unit 1 day’s work of (A+B) = 36/12 = 3 unit 1 day’s work of A = 36/18 = 2 unit 1 day’s work of B = 3 - 2 = 1 unit Now, Time taken by B to completed the work = 36/1 = 36 days
Which country secured the first position in the Global Fish Production 2022?
 Bandhan bank has roped _________ as its brand ambassador for the bank’s product and service endorsement.
What constitutes an unclaimed deposit according to the revised RBI guidelines?
Which class of algae is commonly known as brown algae?
Which Gharana is famous for Sitar players?
When do we observe National Doctors Day annually?
Which freedom fighter from Uttar Pradesh is known as the 'Iron Man of India'?
When did the Portuguese capture Goa from the Bijapur Sultanate?
What was the theme of National Voters’ Day this year?
Who is the Minister of Defence?