Question
1 man and 4 women can complete a work in 65 /4 days,
while 3 men and 4 women can complete it in 13 /2 days. In whom many days will be 13 women complete the work.Solution
1M + 4W = 65/4days 3M + 4W = 13/2days (1M + 4W)65/4 =13/2(3M + 4W) 5M + 20W = 6M + 8W 12W = M 1W = 12M W/M=1:12 Total work = 65/4(12+4) =65/4) ×16 = 260 units 13 women can do this work = 260/13=20days
Under the Pradhan Mantri Suraksha Bima Yojana risk coverage of ________for accidental death and complete disability and _______ for partial disability i...
Organisation behaviour is studied at how many levels?
How many digits are there in MMID issued by the bank upon registration?
How much cash payment can be made to the beneficiary in India under MTSS?
As per RBI draft prudential guidelines for Advances - Projects Under Implementation, Directions, 2024, the LIE must certify the stages of completion of...
During the financial year 2023-24, A had cash sales of ₹3,90,000 and credit sales of ₹1,60,000. His expenses for the year were ₹2,70,000, out of w...
According to the IFSCA Circular issued on January, 2024, what purpose code should be used by AD banks in their Balance of Payments (BOP) file to report ...
Who is the Managing Director (MD) and Chief Executive Officer (CEO) of National Housing Bank (NHB)?
How many financial centers were researched for the GFCI 35, of which 121 are in the main index?
What should be the minimum net worth of Authorized Fund Management entity in IFSC under Fund Management Entity regulations given by IFSCA