Question
A completes 1/3 of a task in 4 days, while B finishes
the remaining work in 8 days. If B is 25% less efficient than C, how many days will A, B, and C together take to complete 5/6 of the task?Solution
Time taken by ‘A’ to complete the whole work = 4 × 3 = 12 days
Time taken by ‘B’ to complete the whole work = 8 × (3/2) = 12 days
Time taken by ‘C’ to complete the whole work = 0.75 × 12 = 9 days
Let the total work be 36 units
Efficiency of ‘A’ = 36/12 = 3 units/day
Efficiency of ‘B’ = 36/12 = 3 units/day
Efficiency of ‘C’ = 36/9 = 4 units/day
Required time taken = (5/6) × (36/10) = 3 days
Which country emerged as India's third-largest export market in the fiscal year 2023-24?
How many new metro projects were inaugurated by Prime Minister Modi in January 2025?
Youth policy of Uttarakhand was established in which year?
By what amount has the monthly nutrition support under Ni-Kshay Poshan Yojana been increased for TB patients during treatment?
Who called Balgangadhar Tilak the father of unrest?
What was the record distance of Neeraj Chopra's winning throw in the men's javelin final at the 2023 World Athletics Championships?
Who was recently appointed as the Additional National Security Adviser (NSA) of India, filling this post for the first time?
Who was recently appointed as the new Secretary of the Telecom Regulatory Authority of India (TRAI)
Bali Jatra is the major Boita Bandana festival of a week celebrated in Cuttack from __________________ .
Match the following in regards to the Aluminium industry and their locations are correct?