A and B together can complete a piece of work in 35 days
while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12.5% of the work.Solution
Time taken by A to complete the whole work = 20/0.50 = 40 days Let total work = 280 units Amount of work done by A and B together in one day = 280/35 = 8 units Amount of work done by A alone in one day = 280/40 = 7 units Amount of work done by B in one day = 8 β 7 = 1 units Desired time = 0.125 Γ 280/1 = 35 days
Who has become India's number 1 chess player?
Archaeologists have unearthed 3,000-year-old priestly tomb in which country?
The University Grants Commission (UGC) has appointed _________________as chairman, of the executive committee of the National Assessment and Accreditati...
Which entity has Adani International Ports Holdings Pvt. Ltd (AIPH) signed the concession agreement with to operate Container Terminal 2?
Which of the following Gharana is known for being the oldest tabla Gharana ?
What recent (April 2024) announcement did the National Stock Exchange (NSE) make regarding derivatives contracts?
Who was the first female Prime Minister of India?
What is the allocation for agriculture and allied sectors in the Union Budget 2024-2025?Β Β
The Union Cabinet recently approved India's participation in the Biodiversity Beyond National Jurisdiction (BBNJ) Agreement. Which ministry will lead th...
Who is known as the originator of the Beej Bachao Andolan (Save the Seed movement) in Uttarakhand?