Question
A, B, and C can finish work in 5 days, 10 days, and 15
days, respectively, working alone. A and B work on the first day, A and C work on the second day, A and B work on the third day, and so on till the work is completed. In how many days the work will be completed?Solution
Working fashion=(A+B) + (A+C) +(A+B) …. Working in 2days = (6+3+6+2) =17 3days =17+9=26unit Remaining work =30-26=4unit Remaining work 4units is done by (A+C) 4days =4/8=1/2 days Total days= 3+1/2=7/2days .
Under which section of the Citizenship Act can an OCI card now be revoked due to criminal charges or chargesheets?
NPCI International Payments Limited (NIPL), a wholly-owned subsidiary of the National Payments Corporation of India (NPCI), has entered into a strategic...
Who is the author of the book "A Part Apart: The Life and Thought of B.R. Ambedkar"?
The seventh Asian men’s Champions Trophy hockey tournament will be held at the _______from August 3 to 12 and will be the first time the tournament wi...
What was the penalty imposed by RBI on Axis Bank for regulatory non-compliance?
The 11th BRICS Labour & Employment Ministers’ Meeting in 2025 was held in which country?
What type of helicopters can INS Tushil carry?
The Employees’ Provident Fund Organisation (EPFO) added 13.40 lakh members on a net basis in March out of which around 7.58 lakh new members have co...
How many new branches has HSBC India received RBI approval to open?
When did the Hayli Gubbi volcano in Ethiopia erupt after 12,000 years of dormancy?