Question

A and B together can complete a piece of work in 32 days while A alone can complete 40% of the work in 32 days. Find the time taken by B to complete 60% of the work.

A 34 days Correct Answer Incorrect Answer
B 36 days Correct Answer Incorrect Answer
C 32 days Correct Answer Incorrect Answer
D 35 days Correct Answer Incorrect Answer
E 30 days Correct Answer Incorrect Answer

Solution

Time taken by A to complete the whole work = 32/0.40 = 80 days
Let total work = 160 units
Amount of work done by A and B together in one day = 160/32 = 5 units
Amount of work done by A alone in one day = 160/80 = 2 units
Amount of work done by B in one day = 5 – 2 = 3 units
Desired time = 0.60 × 160/3 = 32 days