Question
‘A’ alone can complete a work in 15 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 5 days, then the remaining work can be completed by ‘A’ alone in how many days?
More Time and work Questions
- A buffalo alone can plough field ‘A’ in 40 days. A Bull alone can plough the field ‘A’ in 80 days. Find the number of days taken by 3 bulls and 1 buffalo t...
- 'P' and 'Q' together can complete the work in 12 days. 'Q' alone can complete the work in 36 days. If R is 50% more efficient than P, find the time taken b...
- (x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. Find...
- Ashish and Anil can do a piece of work in 20 days and 25 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the r...
- A company hires workers A, B, and C to finish a project. A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days. T...
- ‘A’ is 25% less efficient than ‘B’, and ‘C’ is 75% more efficient than ‘B’. All three together complete a task in 32 days. After ‘A’ and ‘B’ work together ...
- Sam and John can complete a piece of work in 8 days and 12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaining ...
- Sonal completed 30% of work alone and left the remaining work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find ...
- Riya can do a piece of work in 30 days, and Mehul can do it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more effic...
- Together, Ali and Imran take 40 days to complete a project. After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt