Question
25 employees working 9 hours a day take 20 days to complete
a project. How many employees working for 8 hours a day are needed to complete twice the given project in 25 days if they work at 15% higher efficiency?Solution
ATQ,
Let the total work be 'W' units and the efficiency of each employee be 'E' units/hour.
Let the number of employees required be 'M'.
ATQ:
How many people have been selected for Padma bhusan award 2023?
Which of the following statements accurately reflects the approvals granted by the Competition Commission of India (CCI) in July 2024?
A) Transac...
According to the "State of Healthcare in Rural India, 2024" report, what percentage of rural households lack any health insurance?
With whom has the Indian Council of Agricultural Research signed an MoU to empower farmers?
After a prolonged period of hot and dry weather, some parts have been given Drought status by which country recently?
What was the retail inflation, termed as CPI, in March 2024?
How much has the Indian government approved for the 56 new Watershed Development Projects under the PMKSY-WDC 2.0 scheme?
Which state has become the first state to release its own Wildlife Action plan (2021-30).?
What is the primary purpose of the KrishiDecision Support System (KrishiDSS), and what are some of the advanced modules included in this platform?
Who has recently taken charge as the Managing Director & CEO of Bandhan Bank Ltd.?