Question
Carol, Bruce, and Peter can decorate a venue in 7, 14,
and 21 days respectively. If they start working together, but Carol leaves 3 days before completion, Bruce leaves 1 day before, and Peter stays till the end, how many days does it take to complete the decoration?Solution
Carol, Bruce, and Peter can decorate a venue in 7, 14, and 21 days respectively. LCM of 7,14, and 21 =42. Total work =42units The efficiency of Carol =42/7 = 6 units. The efficiency of Bruce =42/14=3 units The efficiency of Peter =42/21=2 units. Suppose the work had not been left by Carol and Bruce. Extra work =6×3+3×1=21 units Total work =42+21 =63units. Time =63/11 =5(8/11) days.
In which country the International Union for Conservation of Nature (IUCN) 'World Conservation Congress' 2025 will be organized?
Central government pensioners aged 80 years and above will receive an additional allowance of:
What is the total approved outlay for the Pradhan Mantri Kisan Sampada Yojana (PMKSY) during the 15th Finance Commission cycle (2021–26)?
What is the name of India’s first co-op university for which the foundation stone was laid in Anand, Gujarat?
As per the latest FIFA rankings, what position does India hold in the men’s rankings, and which country is at the top?
What among the following makes Cochin International Airport Limited (CIAL) claim to be the first airport operator in the world?
Which state bagged gold medal in the 40th India International Trade Fair (IITF) held at Pragati Maidan in Delhi for excellence in display in state gove...
Where is India’s first cable-stayed rail bridge, the Anji Khad Bridge, located?Â
The Henley Passport Index ranks India at which position with visa-free access to 58 countries?
What was SBI’s net profit in FY25?