Question

‘A’ can complete 30% of a work in 3 days. ‘B’ takes 5 days more than ‘A’ to complete the work and ‘B’ is 33⅓% more efficient than ‘C’. ‘A’ started the work alone; on the 2nd day, he is joined by ‘B’ only; on the 3rd day, he is joined by ‘C’ only; on the 4th day, he works alone again, and so on. They worked this way for 6 days. The sum of the time taken to complete the remaining work by ‘A’ alone and by ‘B’ alone is how much percent more/less than that by ‘C’ alone?

A 20% more
B 25% more
C 30% more
D 35% more
E 15% more
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)