Question
If 3 men can finish a task in 4 days, and 4 women can
complete the same task in 9 days, how many days will it take for a team of 2 men and 6 women working together to complete the task?Solution
Time taken by 2 men to complete the work = (3 × 4)/2 = 6 days Time taken by 6 women to complete the work = (4 × 9)/6 = 6 days Therefore, required time = (6 × 6)/(6 + 6) = 36/12 = 3 days
Which of the following is a basic equation used in the COCOMO model?
How many stable states does a positive-edge-triggered D-type flip-flop have?
Basic syntax to create a bar-chart in R is
Which of the following is a component of a combined cycle power plant?
Which are types of system design
Which SQL keyword is used to remove rows from a table?
Which is the correct format specifier for double type value in C?
Which concurrency control technique allows a transaction to read uncommitted data?
keyword is used to skip this iteration and move to next iteration ?
Which type of digital circuit produces an output solely based on its current inputs and doesn't have any memory elements?