Question
Raj, Sanjay and Vaibhav can separately finish a work in
20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by Sanjay and Vaibhav and alternates days starting with Sanjay.Solution
RajSanjayVaibhav 203040 120 643 Working type – (Raj+ Sanjay) (Raj +Vaibhav) Working in first 2 days =10+9=19unit Working in 2×6=12 days =19×6=114unit 13days-6/10=3/5 Total time =12+3/5=63/5days
What is the significance of Zeenat’s translocation to Odisha’s Similipal Tiger Reserve?
CPI inflation in India (August 2025) was recorded at:
On which date World Red Cross Day is celebrated annually?
In April 2026, the Government of India approved a Rs. 30 billion currency swap facility for Maldives under which framework?
Who was given a one-year extension as Director of the Intelligence Bureau till June 2026?
Which of the following is the name of the joint exercise conducted between the Indian and Vietnam Coast Guards?
How many personnel are participating in AJEYA WARRIOR-25 from both Indian and UK armies?
Keki Mistry joined Housing Development Finance Corporation (HDFC Ltd) in which year?
What was the Centre’s fiscal deficit as a percentage of the full-year target in the first half (H1) of FY26?
The government has directed which body to create a coordinated response mechanism for AI-related threats?