      6 men and 6 women can do some work in 3 days. If each

      man is 200% more efficient than a woman, then find the time taken by 12 men to finish the same work together.
      A 3 days Correct Answer Incorrect Answer
      B 2 days Correct Answer Incorrect Answer
      C 4 days Correct Answer Incorrect Answer
      D 5 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of each woman be 'x' units/day. So, efficiency of each man = 3x units/day So, total work = 3 × {(6 × 3x) + (6 × x)} = '72x' units So, required time = 72x ÷ (12 × 3x) = 2 days