Question
A can complete a work in 15 days. B takes 5 days less
than A to complete the same work. In how many days can both of them together complete 60% of the work together?Solution
Time taken by B to complete the work = 15 – 5 = 10 days Let the total work = 30 units Efficiency of A = 30/15 = 2 units/day Efficiency of B = 30/10 = 3 units/day Required time taken = 0.60 x 30/(2+3) = 3.6 days
Which option in Microsoft Word allows you to create a duplicate copy of the selected text or object?
_________ is used to quickly apply the same formatting, such as colour, font style and size, or border style, to multiple pieces of text or graphics.
Mohak Shangle is interested in making a digital presentation for marketing his company's new product using an Open Source Software. Which of the followi...
How can you add a watermark to a document in Microsoft Word?
Which of the following inbox categories helps to focus on the emails that matter the most and separates the inbox into different tabs in MS-Outlook 365?
The name of a word document displays in ____
What is the purpose of the "Animations" tab in PowerPoint?
What does the term "cell" refer to in a spreadsheet?
The default file extension of MS-Excel is
In MS Word 365, which keyboard shortcut is used to cut the selected text?