Time taken by B to complete the work = 15 – 5 = 10 days Let the total work = 30 units Efficiency of A = 30/15 = 2 units/day Efficiency of B = 30/10 = 3 units/day Required time taken = 0.60 x 30/(2+3) = 3.6 days