Question
162 unit of work can be completed by P alone in 27 days. P started working alone and joined by Q after 12 days such that they completed the remaining work in 5 days. Find the number of days taken by Q to complete the whole work alone.
More Time and work Questions
- 30 men can complete 3/5 part of a work in 8 days working 18 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 30...
- 20 men or 40 women can complete a piece of work in 24 days. A man and a woman together complete the work and receive a total wage of Rs. 12,000. Find the d...
- Question 3
- Ajay alone can complete a work in 50 days. Vijay is four times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10...
- 108 unit of work can be completed by P alone in 18 days. P started working alone and joined by Q after 9 days such that they completed the remaining work i...
- A person can complete a work in 15 days, and another person can complete the same work in 20 days. They work together for 5 days, and then the first person...
- Person A can complete 25% of a job in 4 days. Person B is 20% less efficient than Person A. How many days will it take for both A and B, working together, ...
- 12Men and 12women can complete a piece of work in 9 days. 6 men and 15 women can complete the same work in 12 days. How long (in days) would it take 9 wome...
- Arjun, Bharat and Chintu together can complete a task in 8 days. Bharat is 25% less efficient than Arjun. Arjun and Chintu together can complete the task i...
- 6 men and 10 boys can finish a task in 18 days. If each boy is between 1/3rd to equal the efficiency of a man, find the maximum and minimum number of days ...