Question
162 unit of work can be completed by P alone in 27 days.
P started working alone and joined by Q after 12 days such that they completed the remaining work in 5 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (162/27) = 6 units/day According to question: 6 × 12 + (6 + x) × 5 = 162 Or, 72 + 30 + 5x = 162 Or, 5x = 162 – 102 Or, 5x = 60 Or, x = 12 Number of days taken by Q to complete the work alone = (162/12) = 13.5 days
Who was awarded the Man Booker International Prize 2017?
Issuance of which of the following does not bring any additional capital to the company?
Proteins are an integral part of
What is cholesterol among the following?
__________was the capital of Magadha before the 4th century BCE.
Periyar National Park is located in which Indian state?Â
Which animal is engraved on most of the Harappan seals?
India’s first nuclear missile tracking ship INS Dhruv is being built by which organization?
In which year India became a part of the Mineral Security Partnership (MSP), which is led by the USA?
Bordeaux city is famous for ?