Question
162 unit of work can be completed by P alone in 27 days.
P started working alone and joined by Q after 12 days such that they completed the remaining work in 5 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (162/27) = 6 units/day According to question: 6 × 12 + (6 + x) × 5 = 162 Or, 72 + 30 + 5x = 162 Or, 5x = 162 – 102 Or, 5x = 60 Or, x = 12 Number of days taken by Q to complete the work alone = (162/12) = 13.5 days
Which part of the policy includes details such as policy duration and limits of liability?
Name the first life insurance company to function in India?
What is the role of an actuary in the insurance industry?
The Public Sector Insurance companies in India include:
Under which type of plans, an insurance that provides coverage at a fixed rate of payments for a limited period of time is called?Â
Once an insurance company has paid up to the limit, it will pay no more during that year is known as?
Intangible assets cover non-physical assets that cover ________________.
What is the insurance of commercial property that protects the property from such perils as fire, theft and natural disaster?
Which component of an insurance policy includes the name, logo, and contact details of the insurer?
Mortality Charge is the amount charged _____________ by the insurer