162 unit of work can be completed by P alone in 27 days. P started working alone and joined by Q after 12 days such that they completed the remaining work in 5 days. Find the number of days taken by Q to complete the whole work alone.

A 37.5 days
B 46 days
C 13.5 days
D 14 days
E 12 days