Question
168 unit of work can be completed by P alone in 28 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (168/28) = 6 units/day According to question: 6 Γ 10 + (6 + x) Γ 6 = 168 Or, 60 + 36 + 6x = 168 Or, 6x = 168 β 96 Or, 6x = 72 Or, x = 12 Number of days taken by Q to complete the work alone = (168/12) = 14 days
Who won the Global Anti-Racism Championship Award 2024, presented by the US Secretary of State?
Which institute is collaborating with NTPC Vidyut Vyapar Nigam to install rooftop solar panels for boosting solar energy usage in health research facili...
Which online platform launched by the Indian government focuses on disaster resilience in the power sector?
Who among the following is known as the Father of the Indian Constitution?
Arrange the rulers of the Salodaditya dynasty in chronological order
1. Subhiksha Raj
2. Padmadev
3. Desat Dev
4. Ichat Dev
What penalty did the RBI impose on HDFC Bank for violating recovery agent engagement guidelines?
What is the official language of Bihar?
Which Muslim saint is associated with the founding of Fatehpur Sikri?Β
Match the columns correctly and choose the correct answer:
<...
Ghiyasuddin Balban (1265-1286 AD), ruler of the Slave dynasty, took up the title of ____________.