Question
168 unit of work can be completed by P alone in 28 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (168/28) = 6 units/day According to question: 6 Γ 10 + (6 + x) Γ 6 = 168 Or, 60 + 36 + 6x = 168 Or, 6x = 168 β 96 Or, 6x = 72 Or, x = 12 Number of days taken by Q to complete the work alone = (168/12) = 14 days
Sum of three positive numbers is 126. If the ratio of the first and second number is 4:5, respectively while difference between the first and third num...
Three natural numbers X,Y,Z are pairwise co-prime and satisfy the following conditions, the least common multiple (LCM) of X and ...
Find the sum of all natural numbers less than 500 which are divisible by 7.
Sahil can make a toy in 3 hrs, 25 minutes and 13 seconds. How much time he will take to make 8 such toys?
Find the smallest 4-digit number which is exactly divisible by 6, 9 and 15.
- Calculate the largest 5-digit number which is divisible by β64β
What is the average of all the prime numbers which are less than 35?
'M' is the largest three-digit number that leaves 3 as a remainder when divided by 9, 12 and 5, Find the sum of digits of 'M'.
The square of the sum of two numbers is 784. The sum of squares of these numbers is 520. Find their product.