Question
126 unit of work can be completed by P alone in 21 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 4 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (126/21) = 6 units/day According to question: 6 × 10 + (6 + x) × 4 = 126 Or, 60 + 24 + 4x = 126 Or, 4x = 126 – 84 Or, 4x = 42 Or, x = 10.5 Number of days taken by Q to complete the work alone = (126/10.5) = 12 days
Which of the following statement is not correct regarding PM- Awas Yojana Gramin?
Who was awarded the World food prize in 1987?
What are the advantages of Conservation Agriculture?
1. Reduction of production and labour costs is possible.
2. It is possible to em...
The world’s largest coral reef isÂ
Which of the following is also called Golden Fiber?
In India the major forest product is?
Consider the following statements:
- Operation sankalp was launched in 2022 by Indian Navy
- Indian Navy has i...
e-NAM scheme was launched by which ministry?
PM Kisan is a ______ sector scheme launched in _____
World Animal Day is observed 4th October every year and the theme for the same during this year was