Question
180 unit of work can be completed by P alone in 30 days.
P started working alone and joined by Q after 18 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (180/30) = 6 units/day According to question: 6 × 18 + (6 + x) × 6 = 180 Or, 108 + 36 + 6x = 180 Or, 6x = 180 – 144 Or, 6x = 36 Or, x = 6 Number of days taken by Q to complete the work alone = (180/6) = 30 days
What is the central government’s share in the Northeast Centre under Project Bamboo?
The Union Cabinet has extended the period of Pradhan Mantri Garib Kalyan Ann Yojana (PMGKAY) till ______?
Who was honoured with the Icon Award at the London Film Festival in 2018?
Bank of Baroda raised __________ through Basel-III Tier-II bonds with a 10-year maturity period at 7.75% and has received a total of 88 bids amounting...
Who was elected as the new president of the International Court of Justice (ICJ)?
Which campaign was started by the Insurance Awareness Committee to promote life insurance awareness and financial protection in India?
Which of the following brings out the 'Consumer Price Index Number for Industrial Workers'?
Under the "Indira Gandhi Pyari Behna Sukh Samman Nidhi Yojana," what monthly aid will be provided to women above 18 years of age in Himachal Pradesh?
Which of the following has Largest Capacity Factor Ratio –
As of 2022, what was the highest-denomination currency note printed by the Reserve Bank of India?