Question
180 unit of work can be completed by P alone in 30 days. P started working alone and joined by Q after 18 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.
More Time and work Questions
- A man takes 200 days to finish a work alone. If he started working alone and joined by one more man having same efficiency as of him every day from 2nd day...
- Working alone, B can complete the work in 25 days. C is twice as efficient as B and A takes 2.5 days more than it takes C to complete the work. Working tog...
- Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it tak...
- Riya completes 40% of a task in 24 days, while Siya finishes 30% of the same task in 27 days. Riya begins the task alone and stops after 30 days. How long ...
- ‘n’ men working 16 hours a day can complete a work in 10 days while (2n – 4) men working 10 hours a day can complete the same work in 9 d...
- 138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining work ...
- A 480-liter blend contains soap and water in a 5:3 ratio. Adding 60 liters of soap and (6u + 30) liters of water changes the ratio to 6:5. Find the ratio o...
- A buffalo alone can plough field ‘A’ in 40 days. A Bull alone can plough the field ‘A’ in 80 days. Find the number of days taken by 3 bulls and 1 buffalo t...
- A and B can complete a work together in 32 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
- Amit and Anaya can complete a task together in 20 days. If Anaya is 150% more efficient than Amit, how many days will Anaya alone take to finish the task?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt