Question
180 unit of work can be completed by P alone in 30 days.
P started working alone and joined by Q after 18 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (180/30) = 6 units/day According to question: 6 × 18 + (6 + x) × 6 = 180 Or, 108 + 36 + 6x = 180 Or, 6x = 180 – 144 Or, 6x = 36 Or, x = 6 Number of days taken by Q to complete the work alone = (180/6) = 30 days
Etawah Pilot Project was launched under the leadership ofÂ
Which of the following is a technology-based program that was implemented to ensure a direct technological connection between laboratories and the agric...
The concept of Krishi Vigyan Kendra was launched on the recommendation of which of the following committee?
Last people to adopt new practices and are traditional:
The measure of which nutrient's square is found deficient in "Black Soil"?
Which bacterial phylum is one of the most predominant in the phyllosphere?
The PRI level that marks the first point of contact for individuals seeking public services in villages and small towns is the:
Heavy shedding of buds and bolls occurs in cotton due to:
Who was First chairman of “National Commission on Farmers” which started in Feb, 2004
Which one of the following is mass approach in extension and communication?