Question
Ashish and Anil can do a piece of work in 12 days and 16
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 12 and 16) = 48 units Efficiency of Anil = 48/16 = 3 units/day Remaining work = 48 x 0.75 = 36 units Time taken by Anil to complete the remaining work = 36/3 = 12 days
Select the number that is different from the rest.
Which of the following is the annual amount provided to eligible women under the Mahtari Vandan Yojana in Chhattisgarh?
"The State shall take steps to separate the judiciary from the executive in the public services of the State." This is mentioned under ______of Constitu...
Which of the following articles of the Constitution of India mentions that every Minister and the Attorney-General of India shall have the right to spea...
Which of the statements are correct in regards to Priority Sector Lendings (PSL):
1. Agriculture, Micro, Small and Medium Enterprises, H...
What is the naval version of the Iron Dome air defense system called?
The Central Pollution Control Board was set up by the government in the year __________.
Members of which of the following phyla are commonly known as sea walnuts?
In January 2025, which organization received a ₹500 crore capital infusion from the Government of India through a preferential issue of equity shares?
Extremely Severe Cyclonic Storm Tauktae was a powerful tropical cyclone in the _______.