      Question

      Ashish and Anil can do a piece of work in 12 days and 16

      days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.
      A 10.5 days Correct Answer Incorrect Answer
      B 4.5 days Correct Answer Incorrect Answer
      C 9 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 12 and 16) = 48 units Efficiency of Anil = 48/16 = 3 units/day Remaining work = 48 x 0.75 = 36 units Time taken by Anil to complete the remaining work = 36/3 = 12 days