Question
Ashish and Anil can do a piece of work in 12 days and 16
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 12 and 16) = 48 units Efficiency of Anil = 48/16 = 3 units/day Remaining work = 48 x 0.75 = 36 units Time taken by Anil to complete the remaining work = 36/3 = 12 days
What is the name of the 17-year-old girl who became the youngest female to conquer the highest peaks on all seven continents?
 Which of the following is NOT an example of Unicellular organism?
What city was ranked number one in the Economist Intelligence Unit's (EIU) Global Liveability Index for 2024?
Consider the statements about United Nations Statistical Commission:
1. Recently, Sri Lanka started its four-year term as a member of this Commis...
Who has been elected as the Chairman of the Press Trust of India's Board of Directors for a one-year term, marking a significant development in Indian j...
Trilok Singh Basera also known as 'Iron Wall of India' was from which district of Uttarakhand?
Which Bangalore-based start-up has recently obtained a Certificate of Registration from the Reserve Bank of India to operate as an NBFC?
What was the All-India Consumer Price Index (CPI) inflation rate for October 2024?
An Indian Army contingent recently departed for the 13th edition of the joint military Exercise MAITREE. This exercise is conducted with which country?
Harimau Shakti is a joint defense exercise between India and which country?