Ashish and Anil can do a piece of work in 12 days and 16
days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 12 and 16) = 48 units Efficiency of Anil = 48/16 = 3 units/day Remaining work = 48 x 0.75 = 36 units Time taken by Anil to complete the remaining work = 36/3 = 12 days
Identify the first Indian author to win the Andersen Award, celebrated for their contributions to children's literature.Â
The first woman to swim English Channel?
Which part of human brain is responsible for locomotive activities?
The book 'The White Tiger' which won the Man Booker Prize, was authored by:
World Bank will give $_________ million loan to support the Government of Tamil Nadursquo;s Chennai City Partnership: Sustainable Urban Services Programme.
RBI Monetary Policy Committee (MPC) decided to hike the repo rate by how much basis points?
To help passengers track their lost belongings, the Western Railway has launched a service called 'Mission ___________.
India recently overtook United Kingdom to become 5th largest economy in the world according to data collated by _______.
 Gautam Adani: The Man Who Changed India, a book penned down by which of the following?
Who authored the book titled "Unhappy India"?