Question
Ashish and Anil can do a piece of work in 12 days and 16 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the remaining work.
More Time and work Questions
- A is four times as efficient as B and can finish a piece of work in 33 days less than B. B can finish this work in how many days?
- ‘P’ and ‘Q’ together can complete a work in 30 days. If ‘P’ increases his efficiency by 50% and ‘Q’ decreases his efficiency by 50%, then the total time ta...
- A man completes a work in 16 days. A woman finishes half of that work in 10 days. How many days will they take together to finish 75% of the work?
- ‘A’ is 20% more efficient than ‘B’. ‘A’ and ‘B’ work together for 6 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 6 more days to finis...
- ‘A’ and ‘B’ together can complete a work in 12 days, while ‘B’ and ‘C’ together can complete the work in 8 ...
- Amit and Binod receive Rs.1400 for work of 7 days. If Amit is 4 times efficient than Binod, then find the daily wage received by Binod.
- 25 tailors can sew 200 dresses in 40 days by working 5 hours per day. How many tailors are needed to sew the same number of dresses in 25 days by working 8...
- A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450...
- ‘D’ and ‘E’ together finish a task in 20 days. If ‘D’ is 70% more efficient than ‘E’, how many days will ‘E’ take to complete the task alone?
- If Arjun can complete his work in 28 days by working 4 hours a day, how many hours a day should he work to finish the same work in 16 days?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt