Question
A worker finishes 40% of a job in 6 days. At the same
rate, how many more days are needed to finish the remaining work?Solution
40% work → 6 days 1% work → 6/40 days Remaining work = 60% Time for 60% = 60 × (6/40) = 60 × (3/20) = 9 days
Which company became the first Indian firm to surpass ₹10 lakh crore in annual revenue?
Consider the following effects on the foreign exchange rate and identify if they are true or false:
   I. An increase in U.S. demand for Ind...
Which of the following is correct regarding Strategic Risk?
             i.       A Risk arising from adverse business deci...
Consider the following Statements about the Sukanya Samriddhi Account and choose the option with correct Statements.
I- It was launched in 201...
Which of the following components of capital adequacy is/are mandatory as per Basel III norms?
                     I.  �...
What is the primary regulatory body responsible for overseeing financial institutions in Hong Kong?
Consider the following statements.
1)Â Â Â The IFSCA Act empowers the IFSCA to make regulations for the development of financial services in IFS...
The rule of 72 can be used to give an estimate of the time period in which an investment amount can grow by ______, given the annual rate of return.Â
Under the Basel III guidelines, it is advised to create a countercyclical capital buffer of 0-2.5%. Which of the following is not true about this buffer?
 Identify the cash flow from operating activities from the following:
1. Payment of taxes
2. Dividend and Interest payments