Question
60 employees were assigned to complete a task in 45 days. After working for 30 days, it was found that 66.67% of the task had been completed. How many more employees should be added to finish the remaining task on time?
More Time and work Questions
- P, Q and R can finish a job in 45 days, 60 days and 90 days respectively. P and Q work together for 12 days. How long will R take to finish the leftover wo...
- A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the ef...
- Sneha and Meena can complete a project in 24 days and 60 days respectively. Sneha began working first. After how many days should Meena step in so that the...
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- Sneha alone can type a report in 14 days, while Reena can do it in 21 days. If both work together and earn Rs. 14,700 for the job, how much will Reena get?
- A alone can complete 60% of a work in 36 days while B takes 30 days more than A to complete it. If B and C together can complete the work in 40 days, then ...
- Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 6 hours a day can complete a task in 15 days, whereas (3n - 2) women working 5 h...
- There is enough food in a camp to last for 40 days if each of the 60 soldiers present at the camp eat 3 times a day. After 10 days, 10 soldiers left the ca...
- Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many days will it take for six ...
- Suppose Y individuals can complete a task in (Y - 28) days, and (Y + 12) individuals can finish the same task in (Y - 32) days, what is the number of days ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)