      A can finish a work in 18 days and B can finish it in

      24 days. They work together for 6 days, then A leaves. In how many more days will B finish the remaining work?
      A 18 days Correct Answer Incorrect Answer
      B 10 days Correct Answer Incorrect Answer
      C 16 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      ATQ, Aโ€™s rate = 1/18, Bโ€™s rate = 1/24 Together rate = 1/18 + 1/24 = (4+3)/72 = 7/72 Work done in 6 days = 6*(7/72) = 42/72 = 7/12 Remaining work = 1 โˆ’ 7/12 = 5/12 Time for B = (5/12)/(1/24) = (5/12)*24 = 10 days Answer: 10 days