📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A team of 6 workers, each working 8 hours per day, can

      build a 200-metre-long wall in 15 days. How many workers would be needed to construct a 300-metre-long wall in 9 days if each worker only works 4 hours per day?
      A 30 Correct Answer Incorrect Answer
      B 25 Correct Answer Incorrect Answer
      C 12 Correct Answer Incorrect Answer
      D 15 Correct Answer Incorrect Answer

      Solution

      Let required number of men be ‘X’

      Using {(men × hours × days)/work} = constant

      {(6 × 8 × 15)/200} = {(X × 4 × 9)/300}

      Or, {(6 × 8 × 15 × 1.5)/36} = X

      Or, X = 30

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question