      Question

      If the efficiency ratio of A, B, and C is 7:9:11, and B and

      C together can finish a task in 10 days, then how much time will A and B need to complete it?
      A 10.2 days Correct Answer Incorrect Answer
      B 16.5 days Correct Answer Incorrect Answer
      C 19.5 days Correct Answer Incorrect Answer
      D 12.5 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let efficiencies of A, B, and C be 7x, 9x, and 11x units/day respectively.

      Total work = (9x + 11x) ร— 10 = 200x units

      Required time = 200x รท (7x + 9x) = 200x รท 16x = 12.5 days