Question
If the efficiency ratio of A, B, and C is 7:9:11, and B and
C together can finish a task in 10 days, then how much time will A and B need to complete it?Solution
ATQ,
Let efficiencies of A, B, and C be 7x, 9x, and 11x units/day respectively.
Total work = (9x + 11x) × 10 = 200x units
Required time = 200x ÷ (7x + 9x) = 200x ÷ 16x = 12.5 days
Scarcity of capital, unemployment and technological backwardness are generally found in ________ economies.
Which of the following options is correct when we only accomplish two out of three pillars of sustainable development?
Which of the following is/are the objectives of Special Economic Zone (SEZ)?
Which of the statements are correct?
1) Process of disinvestment is very fast
2) Process of disinvestment is very slow and government alwa...
Benefits of Sustainability are?
1) encourages investors interested in working with companies with long-term sustainability plans
2) l...
e-GOPALA App is developed by ______________.
PPP stands forÂ
What does Sustainable Development means?
Which of the following explains the term economic growth?
What is the projected investment under National Infrastructure Pipeline (NIP)?