Question
Anil can do a piece of work in 25 days. He alone worked
at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, they will complete the whole work, working together?Solution
Efficiency of Anil = 100/25 = 4% Work done by Anil in 10 days = 10/25 × 100 = 40% Remaining work = 60% Efficiency of Sunil = 60/15 = 4% Therefore, required number of days = 100/((4+4)) = 100/8 = 12(1/2) days   Â
Economic survey for a year is released on?
A four year mentorship programme ‘Project Arohan’ to provide guidance to students which state government has launched it recently?
How much more muscle mass did the gene-edited lamb show compared to normal sheep?
Consider the following statements about UNESCO's Prix Versailles award:Â
1.     Recently, IGI Airport has won this award.Â
2.  �...
What position has Ajay Singh assumed in the International Boxing Association (IBA)?
Which of the following is NOT included in the PM-Vidyalaxmi scheme's eligibility criteria for students?
What is the primary objective of the Public-Private Partnership (PPP) Beginner’s e-Course launched by the World Bank in collaboration with the Departm...
In November 2021, Oravel Stays Limited (OYO) appointed ___________ as strategic group advisor.
Where is the headquarters of the International Table Tennis Federation (ITTF)?
Who presided over the Monsoon Session 2023 of Rajya Sabha ?