Anil can do a piece of work in 25 days. He alone worked
at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, they will complete the whole work, working together?Solution
Efficiency of Anil = 100/25 = 4% Work done by Anil in 10 days = 10/25 × 100 = 40% Remaining work = 60% Efficiency of Sunil = 60/15 = 4% Therefore, required number of days = 100/((4+4)) = 100/8 = 12(1/2) days   Â
Statements:
All books are erasers.
No sharpener is pencil.
All pencils are books.
Only a few pencils are bright.
Conc...
Statements: B < I ≥ E > K; Z ≤ N = K
Conclusions:
I. Z < E
II. N ≤ I
III. B > N
In the following question below are given some statements followed by some conclusions based on those statements. Taking the given statements to be tru...
Statements:  B & T, K ⋆ B, S ⋆ K
Conclusions:     a) K ⋆ T                b) S # T
...In the following question, a relationship between different elements is shown in the statement followed by two conclusions (I) and (II). Assuming the st...
Read the given statements and conclusions carefully and decide which of the conclusions logically follow(s) from the statements.
Statements:
Statements:Â Â Â Â Â Â K @ L; M & O, N % L, K $ O
Conclusions:Â Â Â Â Â I. O @ LÂ Â Â II. M @ LÂ Â Â Â Â Â Â Â Â III. K # N
...1. Banana price is more than that of lychee.
2. Banana price is less than that of kiwi.
3. Kiwi Price is more than that of banana and lych...
Statement:
Candidates should be young, energetic and dynamic in the age group of 27 to 32 years.
Conclusions:
I. Persons below ...
Many pathogens that cause foodborne illnesses are unknown. Food contamination can occur at any stage from farm to plate. Since most cases of food poison...