Question
Anil can do a piece of work in 25 days. He alone worked
at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, they will complete the whole work, working together?Solution
Efficiency of Anil = 100/25 = 4% Work done by Anil in 10 days = 10/25 × 100 = 40% Remaining work = 60% Efficiency of Sunil = 60/15 = 4% Therefore, required number of days = 100/((4+4)) = 100/8 = 12(1/2) days   Â
Which of the following keyboard shortcuts is used to switch to the last tab of the Chromebrowser?
What is the base of Octal system of coding?
Which of the following functions is not performed by servers?
 Which shortcut key is used to open a new window in chrome incognito mode in chrome ?
What is the role of a proxy server in network security?
The advantage of linked list over array isÂ
Rollback is a term used for ________________.
Embedded computer can be defined as
AÂ _______ operation may give access to the top without modifying the stack.
Which among the following does not form a part of ACID properties with regard to DBMS?