Question
A man takes 200 days to finish a work alone. If he
started working alone and joined by one more man having same efficiency as of him every day from 2nd day onwards, then find the time taken to finish the same work this way.Solution
ATQ, Let the total work be 200x units Efficiency of each man = (200x / 200) = x units/day Total time taken = {n × (n + 1)} ÷ 2 = 200 So, n × (n + 1) = 400 Or, n² + n = 400 Or, n² + n – 400 = 0 Or, n² + 21n – 20n – 400 = 0 Or, n(n + 21) – 20(n + 21) = 0 Or, (n – 20)(n + 21) = 0 So, n = 20 Number of days required to finish the work = 20
Select the odd letters from the given alternatives?
Three of the following four letter-clusters are alike in a certain way and one is different. Pick the odd one out.
Find the odd one out.
In the following question select the odd word from the given alternatives.
Four pairs of numbers have been given, out of which three are alike in some manner, while one is different. Choose out the odd one.
Find out the odd word/letters/number/number pair from the given alternatives.
Find the odd number from the given alternatives.
Three of the following four options are alike in a certain way based on the Alphabetical series. Which one among the following doesn’t belong to the g...
Four letter-clusters have been given, out of which three are alike in some manner and one is different. Select the letter-cluster that is different.
Four letter-clusters have been given, out of which three are alike in some manner and one is different. Select the letter-cluster that is different.