Question
Peter and Rachel can complete a project together in 20 days. Peter takes four times as long as Rachel to complete the same project alone. Find the time taken by Rachel to complete the project alone.
More Time and work Questions
- "Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but Bhanu stops after 4 days, a...
- K and L can complete a work in 16 days. If K alone can complete it in 48 days, how long will L take to complete the work alone?
- X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the valu...
- Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start Kara...
- 4 men and 6 women together or 8 men can complete a piece of work in 20 days. 6 men and 6 women will complete the same work in
- 20 men take 15 days to finish some work. 24 women can finish the same work in 20 days. If the ratio of efficiencies of each man and woman is p:q, respectiv...
- A’ and ‘B’ together can complete a work in 20 days while ‘A’ takes 25 days to complete the same work alone. If ‘C’ is 60% more efficient than ‘B’, then fin...
- In a Construction site Men, Women and Children were working in the ratio 6:3: 1 to finish a job and their individual wages were in the ratio 3:1:2. Entire ...
- 'X' and 'Y' together can complete the work in 16 days. 'Y' alone can complete the work in 24 days. If Z is 50% more efficient than X, find the time taken b...
- A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to work...