Peter and Rachel can complete a project together in 20
days. Peter takes four times as long as Rachel to complete the same project alone. Find the time taken by Rachel to complete the project alone.Solution
ATQ, Let Rachel's time to complete the project alone be 'r' days. Therefore, Peter's time is '4r' days. Their combined work rate is (1/r) + (1/4r) = (1/20). Rachel can complete the project alone in 25 days.
Let a line pass through the origin and make equal angles with the coordinate axes. Then the direction cosines of the line are:
Which of the following scheduling algorithms is designed to reduce the turnaround time and waiting time in a multitasking environment?
The current ages of Shivani and Shilpa are in the ratio 7:5. Shipra's present age is 20% more than what Shilpa's age was five years ago. If the average ...
If z=2+3i, then arg(z)=θ lies in which quadrant?
If a hyperbola passes through the point (4, 0) and has foci at (±5, 0), and the length of its conjugate axis is 6, then the eccentricity is:
The line graph given below shows the number of units of four different Coins sold. Read the graph carefully and answer the question that follows:
...If Seema had run at a speed of 14 km/hr instead of 7 km/hr, she would have covered 20 km more distance. What would have been the actual distance cover...
In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between x and y and choose the...
Marked price of an article is Rs. M, as it is marked by a certain price. Find the value of M.
Statement I. If the shopkeeper gives a discount of ...
Two points A and B are located such that the distance between them is 100 meters. If point A is at the origin and point B is at an angle of 30 degrees f...