Question
Peter and Rachel can complete a project together in 20
days. Peter takes four times as long as Rachel to complete the same project alone. Find the time taken by Rachel to complete the project alone.Solution
ATQ, Let Rachel's time to complete the project alone be 'r' days. Therefore, Peter's time is '4r' days. Their combined work rate is (1/r) + (1/4r) = (1/20). Rachel can complete the project alone in 25 days.
- What is the current estimated bilateral trade value between India and Ireland?
The World’s longest Metro line opened in the country?
What is the name of Oman’s first national communications satellite?
Which institute will launch its new campus in Delhi with courses for working professionals and entrepreneurs.aiming to tap people who want to pursue man...
Recently Securities and Exchanges Board of India (SEBI) makes OTP validation a must for mutual fund investments from which Financial year?
What was the purpose of bringing the Indian Cyber Crime Coordination Centre (I4C) under Section 66 of the PMLA?
Who won the Miss India Worldwide 2024 title?
The newly launched "One India-One Ticket" initiative by IRCTC and NCRTC is aimed at improving the travel experience on which transportation systems?
The 11th Session of the India-Russia Working Group on Modernization & Industrial Cooperation was co-chaired by Amardeep Singh Bhatia and:
Recently the central government has set up the Cotton Council of India, It will be chaired by?