Question
‘A’ and ‘B’ can complete a certain work in 10
days and 15 days, respectively. They started working together and worked till completion of the work for which they got Rs. 16000 as wage. Find the share of ‘B’ out of total wage.Solution
Let total work = 30 units {LCM of (10 and 15)} Efficiency of ‘A’ = 30/10 = 3 units/day Efficiency of ‘B’ = 30/15 = 2 units/day Wages received by ‘A’ and ‘B’ will directly proportion to their efficiency. So share of ‘B’ = 16000 × (2/5) = Rs 6400
Which country secured the first position in the Global Fish Production 2022?
Bandhan bank has roped _________ as its brand ambassador for the bank’s product and service endorsement.
What constitutes an unclaimed deposit according to the revised RBI guidelines?
Which class of algae is commonly known as brown algae?
Which Gharana is famous for Sitar players?
When do we observe National Doctors Day annually?
Which freedom fighter from Uttar Pradesh is known as the 'Iron Man of India'?
When did the Portuguese capture Goa from the Bijapur Sultanate?
What was the theme of National Voters’ Day this year?
Who is the Minister of Defence?